Week 4

Designed DexUMI, integrated eFlesh control, head camera tracking


Week 3

Integrated custom sensors with robot, publish to ROS, teleoperate robot


Week 2

Built version 1 of the eFlesh sensor, set up ROS project and infrastructure, started data collection pipeline


Week 1

Project kickoff, robot setup, ordered components, researched imitation learning methods